Trentham Padel Venue: Executive Summary and Master Index

Project: Six-court indoor padel venue, Stoke-on-Trent / Trentham area Prepared for: Ade Whetton Operating hypothesis tested: lean/unmanned-first operation Size benchmark: Your Padel, Uttoxeter (planning case approximately 3,000–3,200 m² internal) Research date: 7 August 2026 Status: Summary of a 13-document pack (00–12). All figures below are planning-level values carried from the underlying documents with their caveats; none is a quotation or forecast.

Verdict in one sentence: The venue is viable as a gated, conditional programme — hybrid-staffed at opening with unmanned-lean as the earned target state — but it is not yet a go on market evidence alone: the pack's spend rules require planning, utilities-capacity, slab and life-safety gates to close, and demand to be proven against an already-competitive local supply, before any irreversible commitment.


1. What the pack concludes

The core hypothesis survives, trimmed. Ade's central premise — a padel venue does not need someone permanently sitting at reception to take payments, issue rackets or turn lights on — is supported by the evidence (document 09). What the evidence does not support is the fiction that automation removes cleaning, emergency response, safeguarding, stock, maintenance, coaching or compliance. "Unstaffed" means no permanent front desk, not no accountable person.

Recommended operating model: open hybrid, target lean (documents 03, 07, 09). The hybrid case uses five employees across 3.25 payroll FTE, staffs approximately 59 of 108 public clock-hours per week, and confines juniors, coaching, alcohol, events and higher-risk work to staffed blocks; routine booking, entry, lighting, payments and first-line fault triage are automated or remote. Its all-people/service envelope is approximately £278,253/year — roughly £335,039/year below the 21-person traditional design — while the fully lean case (1.5 FTE, 88 remote public hours/week) saves a further ~£83,667 but is rejected as the opening proposition. The design team targets the lean energy profile from day one: booking-linked court lighting, zoned HVAC, and no fully conditioned high-bay hall without board approval, because the conditioned/staffed utility case runs approximately £300,000/year above the lean case (£168,391 vs £468,785; hybrid base £303,038 including rates on illustrative values).

Vending-first pilot (document 01). Commission a controlled 90-day pilot: a 15–18-bay audited racket-rental locker plus one separate cashless consumables machine — not an oversized all-in-one unit, and no five-year non-cancellable contract until real Trentham demand, failure rates and service response are measured. All-in pilot budget £12,846–£28,865 (base £19,195); the illustrative base model shows £35,640 annual gross sales, £12,246 operating contribution and 1.6-year simple payback — planning outputs on editable assumptions, not forecasts. Alcohol is excluded from vending permanently.

The statutory reality check (documents 06, 07 and the validated notes). Indoor padel is Use Class E(d) — a main town-centre use. A 35,000–45,000 sq ft venue (3,252–4,181 m²) exceeds the 2,500 m² national default impact-assessment threshold, so an out-of-centre industrial unit needs a sequential test and impact case, not just a change-of-use form. Assume 20–32 weeks from first consultant instruction to usable consent (13-week statutory target for major development). The cheap fees mislead: the statutory change-of-use fee is £610, but the professional planning and survey package is allowed at £20,000–£60,000. The biggest hidden exposures are infrastructure, not licences: DNO electrical upgrade screened at £10,000–£300,000, water/sewer reinforcement at £5,000–£100,000 / £5,000–£75,000 — all to be resolved or allocated as lease conditions precedent, never absorbed as tenant contingency. Core compliance setup carries a £57,181 base allowance (range £20,256–£168,231) with £39,850/year base recurring; the £712,880 conditional exposure is a screening envelope whose triggers are eliminated before lease, not a budget line. Alcohol needs a premises licence (apply 8–12 weeks before service; staffed service only), food registration goes in free at least 28 days before trading, and the venue opens on evidence, not on a date — the no-go rule.

Market position (document 02). Trentham is plausible but not unserved: Powerleague operates four covered courts at Trentham Lakes, Ace Padel four indoor courts in Cobridge with a Fenton scheme announced, plus Stafford, Draycott and Uttoxeter regionally. A new venue must win on fully indoor quality, availability, programming, hospitality and experience — vending is operationally valuable but is not a moat. No verified, immediately available Trentham building passed every screening gate at research date.

Delivery discipline (document 12). The whole programme runs on document 06's Gates 0–9: heads of terms and desktop money first; planning, surveys and utilities as conditions precedent; court manufacture only after consent risk is controlled; commissioning evidence before automation is trusted; a controlled soft launch behind the no-go rule; and a 90-day reset before any staffed block is cut towards the lean target. Contingency is pre-planned: a staffed fallback if the unmanned technology fails acceptance, and a sport-led hybrid opening (courts, café, vending; bar closed) if the premises licence is delayed.


2. Master index

Doc Title Purpose in one line Status
00 Executive Summary and Master Index This document — the pack's verdict, recommended model and navigation Built post-Manus
01 Vending and Equipment Rental Blueprint 90-day vending pilot design: locker + consumables machine, costed with workbook, supplier and compliance controls Complete
02 Catchment, Competition and Site Screening Market evidence, competitor verification, authority/boundary position and site go/no-go screening criteria Reconstructed tail
03 Operating Model and Customer Journey Hybrid operating principle and the end-to-end customer journey from discovery to close Complete
04 Remote Operations Technology Architecture Access, CCTV, monitoring and failure playbooks — life safety independent of cloud, local control survives WAN loss Reconstructed tail
05 Booking, Payments and Software Stack Federated stack: Playtomic Champion, Square, separate unattended payments, venue-controlled reporting and contract non-negotiables Reconstructed tail
06 Premises, Planning, Building, Fire and Licensing Blueprint The statutory spine: Gates 0–9, Class E(d) planning route, sequential/impact tests, Building Regulations, fire and licensing Reconstructed tail
07 Environmental Health, Water, Waste, Utilities and Council Obligations The 67-obligation operating layer: food, water/Legionella, waste, energy, rates, lease conditions precedent and the no-go rule Complete
08 Café, Bar, Club Shop and Supplier Operations Staged hospitality: hybrid case capex £104,720, contribution £11,856/year — support the venue, never drive the property decision Complete
09 Lean, Hybrid and Traditional Staffing Scenarios Honest coverage economics: lean £194,586 / hybrid £278,253 / traditional £613,292 all-people envelopes; hybrid recommended Complete
10 Master Financial Model and Break-Even Analysis Integrated capital, operating and break-even model across lean/hybrid/traditional; the utilisation-required test doesn't exist anywhere else in the pack Complete (built post-Manus)
11 SOP Library, Compliance Registers and Training-Video Plan 58 SOPs across 15 domains (staffed and unstaffed variants), 27 compliance registers, 8 incident playbooks, a 25-video training suite (V01–V25) mapped to SOPs Complete (built post-Manus)
12 Turnkey Launch Roadmap, Governance and Contingency Phased critical path across all gates, decision rights, spend tiers, top-10 risk register and fallback plans Complete (built post-Manus)

Supporting material in this pack: validated findings notes (notes/ — statutory, master cost, environment, staffing, vending, hospitality, booking/payments, architecture, Uttoxeter benchmark, Trentham market scans) and four recalculated workbooks (models/ — vending pilot, staffing and coverage, hospitality/retail, environmental/utilities obligation register).

Status key: Complete — full Manus deliverable as exported. Reconstructed tail — the export truncated the final section; the ending was reconstructed and should be re-verified against the notes before external use. Built post-Manus — authored after the Manus session ended, from the validated sources in this pack.


3. How to use the pack

  1. Deciding whether to proceed at all: read this summary, then document 02 (market) and document 12 §4 (pause triggers).
  2. Evaluating a candidate building: document 02 §screening, document 06 §2–3 (planning route and heads of terms), document 07 §10 (lease conditions precedent).
  3. Budgeting: document 10 — the integrated capital, operating and break-even model. Its individual module owners, for tracing any single line back to source, are the master cost notes (courts, fire), 07 (compliance/utilities/rates), 09 (people), 08 (hospitality), 05 (software), 01 (vending) — each carries explicit double-counting boundaries; do not add overlapping allowances.
  4. Running the programme: document 12 end to end, with document 06's gate table as the spend authority and document 07's no-go rule as the opening authority.
  5. Training staff and operating from day one: document 11 end to end — the SOP catalogue (§3), compliance registers (§4), incident playbooks (§5) and the numbered training-video plan (§6); its own §7 gives the implementation order for the first SOPs and videos needed before the unstaffed pilot can open.